Airpark Projects
England Airpark Construction & Demolition Areas
FBO Ramp
Rehabilitation consist of the ramp in front of the FBO which is approximately 1150’ x 300’ and replacing 14” of concrete
Cost $7,039,252: approximately 50% State Funding and 50% Federal Funding
Approximately 68% complete
Engineers: Meyer, Meyer, Lacroix & Hixson
Contractor: Gilchrist Construction
Runway 18/36 Midfield Overlay
Rehabilitation consist of overlaying approximately 1600’ x 150’ of 4” asphalt at the midfield section of Runway 18/36
Cost $2,100,000: approximately 50% State Funding and 50% Federal Funding
Approximately 99% complete
Engineers: Pan American Engineers
Contractor: Gilchrist Construction
Construction of New Fuel Farm
Project consist of construction a new fuel farm on the south west corner of the south ramp capable of downloading 6 million gallons within 72 hours
Cost $6,100,000: approximately 34% State Funding and 66% Federal Funding Approximately 98% complete
Engineers: Pan American Engineers
Contractor: Tudor Construction
Construction of Fuel Farm Access Road
Project consist of approximately 1500’ of a new 8” concrete roadway way from Chennault Avenue to the new fuel farm location
Cost $1,187,645: approximately 34% State Funding and 66% Federal Funding
Approximately 73% complete
Engineers: Pan American Engineers
Contractor: Gerace Construction
Photos of Demolition at England Airpark
Demolition of the old dormitories as part of our continued efforts on the Master Plan.